Hello folks,
Fada was launched early May.
Taken of the water late October for the winter.
Rowed for 194.54km, 45h53m.
Here are some points that may be useful to you.
Kind regards.
T
Hello folks,
Fada was launched early May.
Taken of the water late October for the winter.
Rowed for 194.54km, 45h53m.
Here are some points that may be useful to you.
Kind regards.
T
To prevent the sliding seat from overshooting the ends of the rails.
Two loop of cord, one port side, the other on starboard.
The cord captures the two axles of the seat, then passes via the two holes (the holes for the t-bolts fixing the rail).
The loop is sized so that it comes tight when the seat _approaches_ the end of range on the rails, Such that all the stretch in the loop is maxed out when the seat is _at_ the end of range.
The loop size is adjusted using the hybrid bowLine/sheetBend knot.
Geometry is important! This works because the centres point between the two t-bolt slots is directly below the centre point of the rail.
Port and Starboard because when the seat is at end of range the loop is under a little bit of tension, pulling on one side od the seat. If only one loop, then this unbalanced tension will distort the seat over time.
Fixing the drop in sliding seat.
I built acording to the instructions, so two fixings are required. Out of prudence I carry three. When not in use I stow all three attached to the drop in mechanism. When in use two will fix the drip in mechanism to the floor of the cockpit pit, the third will remain stowed.
Regarding the bracket fixed to the floor of the cockpit, here I deviated from instructions. I made it large ento have a _snug_ fit to the drop in, to prevent an unwanted left-right movement.